The IBM z/VM JOURNALING statement must be coded on the configuration file.
Overview
| Finding ID | Version | Rule ID | IA Controls | Severity |
| V-237930 | IBMZ-VM-000810 | SV-237930r858994_rule | CCI-001464 | medium |
| Description | ||||
| If auditing is enabled late in the start-up process, the actions of some start-up processes may not be audited. Some audit systems also maintain state information only available if auditing is enabled before a given process is created. | ||||
| STIG | Date | |||
| IBM zVM Using CA VM:Secure Security Technical Implementation Guide | 2022-08-31 | |||
Details
Check Text (C-237930r858994_chk)
Examine the Product configuration file.
If the "JOURNALING" statement does not specify "ON", this is a finding.
Fix Text (F-41099r858993_fix)
Configure the system configuration "JOURNALING" statement to "JOURNALING ON".